Friday, July 24, 2009

Taping and Painting

Taping is now complete and the main and second floors have been primed. View from the loft:


Second floor bathroom:

The cork floor was also delivered this week:

Wednesday, June 24, 2009

Drywall, Taping and Decks

Drywall is now complete for the entire house. Taping is ongoing for the main and second floors and will start soon in the basement.

Our deck and front steps are also framed. The front steps will require a guardrail. The rear deck will not as it's less than 2' above grade.

Tuesday, June 2, 2009

Cladding and Basement Framing

Cement board cladding is now complete. The basement framing was also completed at the beginning of the month. Electrical and mechanical rough in will happen next and we'll try to catch the basement up to the rest of the house during the drywall stage.


Sunday, May 10, 2009

Spray Foam Insulation

We had the underside of the roof and the joist ends on all levels insulated using a closed cell structure spray foam insulation. The product is made using a soybean oil and recycled plastic bottles, and provides an R value of R7 per inch thickness
.

Sunday, May 3, 2009

Cement Board and Batt Insulation

The cement board panel installation is almost complete, with only the top half of the front face remaining. With the correct front door finally installed, the cedar siding was able to be finished.

Batt insulation was installed this week in the exterior walls. We are spraying the roof with a closed cell insulation that allows us to achieve the unvented soffit and no overhang detail. The spray foam is scheduled for next week.

Friday, April 17, 2009

Basement Slab and Cement Board Panel Install


The basement slab was poured this week. Our goal is to get it framed, plumbing and electrical roughed in, and insulated so that the entire house can be drywalled at the same time.

Cement board siding installation has also started. The panels are 4x8' in size and installed vertically. Our replacement front door also arrived this week - it's under the blue tarp in the photo above.

Friday, April 10, 2009

Garage Door and Basement Slab Prep


The garage door was installed this week. This is nice as it gives us more secure storage during construction. We also had power service hooked up so we don't have to depend on the neighbor anymore. The basement slab will be poured soon - this photo shows the leveling of the gravel base. We're going to remove about an inch of the gravel to provide more space for the rigid insulation that will be placed on top (our goal is to maximize the ceiling height).