Friday, September 4, 2009

Rails and Second Floor Bath Progress



The metal rails were fitted and installed. Measurements were taken so that the glass can be ordered for the loft guardrail. We will be taking the exterior railing off the front porch to get powdercoated. The interior rails will be painted.


The second floor bath is also showing progress. Both floor tile and mosaic wall tile are finished, and the vanity is in place so that countertops can be measured. Special thanks to Dave for the beautiful custom vanities!

Thursday, August 20, 2009

Paint and Tile

Interior painting was finished this week, which includes the walls, ceilings, exterior doors, and clear sealing the wood window frames. There is one accent colour: a medium grey painted on the wall that separates the stairs on all three levels.



Tile installation began yesterday. Here's a photo of the wall tile in the basement bathroom:


Floor tile and preparation for wall tile in the upstairs bathroom:

Friday, August 14, 2009

Cork Floor Completed



Installation of the cork floor on the main and second floor was completed this week. The installer also mocked up the mitred stair detail to ensure it will work. We've decided to wait until everything else is completed (including furniture moved in) to complete the stairs.

Thursday, August 6, 2009

Flooring and Finish Carpentry



The cork floor install started today. The cork floor will be throughout the main floor and second floor, with the exception of the upstairs bathroom.


The first phase of the finish carpentry was also completed, which includes interior doors, casings, and closet shelving.

Sunday, August 2, 2009

Concrete and Basement Painting

Exterior concrete work was poured this week, including the front walkway, window well, landing at the side entrance, and driveway pad. The remaining cement board panels have also been installed. The grey panels will be painted white to match the others - for some reason they did not ship pre-painted this time.

Priming is also finished in the basement. A coating was also applied to the ceilings to provide a smooth finish for painting (as the ceilings will not be textured). We are protecting the basement slab as we intend to leave it exposed and seal it as the finished floor.

Friday, July 24, 2009

Taping and Painting

Taping is now complete and the main and second floors have been primed. View from the loft:


Second floor bathroom:

The cork floor was also delivered this week:

Wednesday, June 24, 2009

Drywall, Taping and Decks

Drywall is now complete for the entire house. Taping is ongoing for the main and second floors and will start soon in the basement.

Our deck and front steps are also framed. The front steps will require a guardrail. The rear deck will not as it's less than 2' above grade.