Tuesday, December 2, 2008
Windows and stairs
Our window package arrived last week. As the company we ordered them from are not equipped to deliver the windows, we rented a truck and delivered them ourselves. The doors should arrive in the next week. The stairs were delivered to site last week and installed yesterday.

Mechanical and Plumbing
Saturday, October 25, 2008
Second Floor Framing
Tuesday, October 21, 2008
Main Floor Framing
Most of the main floor walls were framed yesterday. The tall walls at the front of the house will be framed after the second floor walls are in place. We also rented a construction fence, as we heard from a neighbour that some people tried to "borrow" some of our lumber in the middle of the night.

Framing
The front yard was backfilled last week. The joist and framing packages were also delivered. We were unable to have the rear of the lot backfilled because the framing package was delivered right smack in the middle of the back yard. One of the challenges of a small lot is construction staging.

The main floor of the house was framed just in time for the weekend:


The main floor of the house was framed just in time for the weekend:
Tuesday, October 7, 2008
Drainage Board & Weeping Tile
We decided to go with the Delta MS drainage board for foundation protection instead of the usual dampproofing. It is a dimple sheet that diverts water down to the weeping tile. This is what it looks like:
Friday, October 3, 2008