Landscaping is in progress. The trees and sod have been placed and the turfstone parking pad installed. We are using prefinished corrugated metal for the fence on the sides and vertical cedar at the front and back (not yet installed).
Wednesday, November 18, 2009
Monday, September 21, 2009
Kitchen and Floor Install
The IKEA kitchen cabinets were installed last week. Underneath the blue protective plastic are high gloss white cabinet doors.
Cork floor install was also completed on the stairs.
We chose to go with concrete countertops in the kitchen and bathrooms. Here's a photo of the countertop after it has been installed and received a finish coat.
Cork floor install was also completed on the stairs.
We chose to go with concrete countertops in the kitchen and bathrooms. Here's a photo of the countertop after it has been installed and received a finish coat.
Saturday, September 12, 2009
Electrical and Grading
Rough and final grading was completed this week. We've scheduled the surveyors to prepare the grading certificate and want to ensure that grading is approved by the City before beginning landscaping.
Electrical finishing started today. Most of the lights, electrical receptacles, smoke detectors, doorbells, etc. were installed. The remaining items will be completed after countertops, tile backsplash, and mirrors are completed.
Electrical finishing started today. Most of the lights, electrical receptacles, smoke detectors, doorbells, etc. were installed. The remaining items will be completed after countertops, tile backsplash, and mirrors are completed.
Friday, September 4, 2009
Rails and Second Floor Bath Progress
The metal rails were fitted and installed. Measurements were taken so that the glass can be ordered for the loft guardrail. We will be taking the exterior railing off the front porch to get powdercoated. The interior rails will be painted.
The second floor bath is also showing progress. Both floor tile and mosaic wall tile are finished, and the vanity is in place so that countertops can be measured. Special thanks to Dave for the beautiful custom vanities!
Thursday, August 20, 2009
Paint and Tile
Interior painting was finished this week, which includes the walls, ceilings, exterior doors, and clear sealing the wood window frames. There is one accent colour: a medium grey painted on the wall that separates the stairs on all three levels.
Tile installation began yesterday. Here's a photo of the wall tile in the basement bathroom:
Floor tile and preparation for wall tile in the upstairs bathroom:
Tile installation began yesterday. Here's a photo of the wall tile in the basement bathroom:
Floor tile and preparation for wall tile in the upstairs bathroom:
Friday, August 14, 2009
Cork Floor Completed
Thursday, August 6, 2009
Flooring and Finish Carpentry
Sunday, August 2, 2009
Concrete and Basement Painting
Exterior concrete work was poured this week, including the front walkway, window well, landing at the side entrance, and driveway pad. The remaining cement board panels have also been installed. The grey panels will be painted white to match the others - for some reason they did not ship pre-painted this time.
Priming is also finished in the basement. A coating was also applied to the ceilings to provide a smooth finish for painting (as the ceilings will not be textured). We are protecting the basement slab as we intend to leave it exposed and seal it as the finished floor.
Priming is also finished in the basement. A coating was also applied to the ceilings to provide a smooth finish for painting (as the ceilings will not be textured). We are protecting the basement slab as we intend to leave it exposed and seal it as the finished floor.
Friday, July 24, 2009
Taping and Painting
Wednesday, June 24, 2009
Drywall, Taping and Decks
Tuesday, June 2, 2009
Cladding and Basement Framing
Sunday, May 10, 2009
Spray Foam Insulation
Sunday, May 3, 2009
Cement Board and Batt Insulation
The cement board panel installation is almost complete, with only the top half of the front face remaining. With the correct front door finally installed, the cedar siding was able to be finished.
Batt insulation was installed this week in the exterior walls. We are spraying the roof with a closed cell insulation that allows us to achieve the unvented soffit and no overhang detail. The spray foam is scheduled for next week.
Batt insulation was installed this week in the exterior walls. We are spraying the roof with a closed cell insulation that allows us to achieve the unvented soffit and no overhang detail. The spray foam is scheduled for next week.
Friday, April 17, 2009
Basement Slab and Cement Board Panel Install
The basement slab was poured this week. Our goal is to get it framed, plumbing and electrical roughed in, and insulated so that the entire house can be drywalled at the same time.
Cement board siding installation has also started. The panels are 4x8' in size and installed vertically. Our replacement front door also arrived this week - it's under the blue tarp in the photo above.
Friday, April 10, 2009
Garage Door and Basement Slab Prep
The garage door was installed this week. This is nice as it gives us more secure storage during construction. We also had power service hooked up so we don't have to depend on the neighbor anymore. The basement slab will be poured soon - this photo shows the leveling of the gravel base. We're going to remove about an inch of the gravel to provide more space for the rigid insulation that will be placed on top (our goal is to maximize the ceiling height).
Friday, March 20, 2009
Cedar siding
The house has been wrapped in Tyvek and some of the cedar siding has been installed. The cedar areas on the front elevation can't go up until our front door unit is replaced with the correct one. The primary cladding of the house is going to be 4 x 8' cement board panels painted white. The material is scheduled to arrive at the end of next week.
We also insulated and installed the vapor barrier in the upstairs bathroom so that the bath tub plumbing can be installed prior to the insulation in the rest of the house.
March Update
Now that it's finally above -30C degrees outside we hope the pace of construction will pick up. Here are some progress photos since the last update:
The holes for the window wells did get excavated in the frozen ground conditions with a jackhammer. We will be using conventional corrugated metal wells for the side windows and a custom timber window well in the front yard.
The front door and window combination was also installed. Unfortunately, the wrong door swing was ordered. The hinges are supposed to be against the wall, not on the centre mullion. The replacement door is scheduled to arrive March 24th.
A temporary furnace has been hung in the basement. Once the gas meter is installed, we will be able to provide temporary heat, allowing us to pour the basement floor slab and insulate the roof with spray foam insulation.
Subscribe to:
Posts (Atom)