Wednesday, June 24, 2009

Drywall, Taping and Decks

Drywall is now complete for the entire house. Taping is ongoing for the main and second floors and will start soon in the basement.

Our deck and front steps are also framed. The front steps will require a guardrail. The rear deck will not as it's less than 2' above grade.

Tuesday, June 2, 2009

Cladding and Basement Framing

Cement board cladding is now complete. The basement framing was also completed at the beginning of the month. Electrical and mechanical rough in will happen next and we'll try to catch the basement up to the rest of the house during the drywall stage.